The building permit

A building permit shows that work was authorized under the state construction code, not that the work was built, inspected or finished.

What a building permit records

A building permit records that an enforcing agency (the local government body, or the contractor acting for it, that administers the state construction code in a given place) gave permission for specific work at a specific address. It shows that someone applied and was authorized; it does not show that the work was built, inspected or finished to code.

In Michigan the permit system rests on 1972 PA 230, the Stille-DeRossett-Hale Single State Construction Code Act. Under the Act, the construction code is enforced locally by a city, village, township or county building department, or by the state where no local unit does so. A permit file usually holds the application, the plans or a description of the work, the code edition applied, the fee receipt and, later, a record of each inspection requested and its result. The permit is the first entry in that file, not the last.

Separate permits are normally issued for building, electrical, plumbing and mechanical work. A single project, such as an addition to a lake cottage, can therefore generate four permit records with four different histories, and one can be closed while another stays open.

Who issues permits around Cadillac

There is no single permit office for the Cadillac area. As published by Wexford County in 2025, the county building department issues building, plumbing, mechanical and electrical permits for every part of Wexford County with three exceptions.

  • City of Cadillac. The city issues its own building, mechanical, plumbing, electrical and soil erosion permits. It has retained a private contractor to provide all of its building permit and inspection services. Applications go to City offices at 200 N. Lake Street, where the Community Development Department handles intake and payment; as published in 2025, only trade permits are accepted through the city's online portal.
  • Cedar Creek Township. The township issues its own building permits.
  • City of Manton. The city issues its own building permits.
  • Everywhere else in Wexford County. The Wexford County Building Department, at 401 North Lake Street in Cadillac, issues the permits.

The state Bureau of Construction Codes is not the enforcing agency for these units. In neighboring counties the arrangement differs: LARA's Statewide Jurisdiction List, revised October 9, 2023, shows every unit in Missaukee County and in Lake County with the county as enforcing agency for all four trades. The practical point for a reader holding a permit is that the issuing office named on it is the office that holds the rest of the file.

The code behind the permit

A residential permit issued in Wexford County authorizes work under the 2015 Michigan Residential Code, which took effect February 8, 2016. LARA's Bureau of Construction Codes still listed it as the current code when its code-books page was checked in November 2026. Commercial work in the county falls under the 2021 Michigan Building Code, and electrical work under the 2023 National Electrical Code, effective March 12, 2024.

A newer residential code was scheduled. The 2021 Michigan Residential Code and its residential energy rules were filed on May 1, 2025, with an effective date of August 29, 2025. On July 7, 2025, before that date arrived, the Michigan Court of Claims stayed them in suits brought against LARA by the Home Builders Association of Michigan and the Michigan Manufactured Housing Association. As of November 2026 the 2015 code remains the one in effect. Because the litigation was pending, anyone relying on this point should check the current status with LARA or the enforcing agency.

Wexford County also applies local design criteria on top of the code: trusses and rafters designed to a 60 pounds-per-square-foot ground snow load, and footings at least 42 inches below final grade. Those are the county's own requirements, not a statewide table, and a permit from another county may carry different figures.

Deadlines, exemptions and expiration

The statute sets the clock for the decision. Under MCL 125.1511, the enforcing agency must grant or deny a permit application within 10 business days, or 15 business days for an unusually complicated building, and failure to act is treated as a denial for purposes of appeal. The companion section, MCL 125.1510, requires no permit for ordinary repairs or for a building incidental to agricultural use.

Expiration is a different matter, and the source is commonly confused. The 180-day rule is in the residential code, not in 1972 PA 230. Section R105.5 of the 2015 code provides that a permit becomes invalid if the authorized work is not started within 180 days of issuance, or if work is suspended or abandoned for 180 days after it starts; the building official may grant written extensions for justifiable cause. Wexford County's Building Information Packet adds that a permit will be cancelled if no inspections are requested or performed within six months of issue, and that extensions beyond 18 months are at the County Building Official's discretion.

Local practice varies. Missaukee County, for example, has treated new permits as valid for one year since January 1, 2025, with one extension and a two-year maximum. A permit record therefore has to be read against the rules of the office that issued it.

What a building permit does not establish

A permit is an authorization. On its own it says nothing about what was eventually built.

  • Completion. Work may have been started and abandoned, or never started at all.
  • Inspection. The permit does not show that any inspection took place, or that one passed. Inspection results are separate entries in the file.
  • Conformity to the plans. What was built may differ from what was described in the application.
  • Final approval. Final sign-off appears as a final inspection or a certificate of occupancy, a separate record under MCL 125.1513.
  • Other work. A permit for a deck says nothing about an unpermitted basement finish or a later addition.
  • Systems outside the construction code. Wells and septic systems are permitted by the health department, not by the building department, and soil erosion and shoreline work carry their own permits.

Where building permit records are commonly misread

The most common misreading treats an issued permit as proof of finished, approved work. A permit can be open, meaning issued with no final inspection, for years after the work appears done. An open or expired permit is a fact about the file, and what it means for a given house is a question for the issuing office.

A second misreading runs the other way: that the absence of a permit proves work was illegal. Ordinary repairs need no permit, and in Wexford County accessory structures under 200 square feet and under 10 feet high need no building permit, although zoning approval is still required. Records for older work may also be incomplete. A missing permit is a gap to ask about, not a finding.

A third is looking in the wrong office. A permit for a house inside the Cadillac city limits sits with the city, not the county; a house in Cedar Creek Township or Manton has its permits with those units. The county's list of exceptions is published on the Wexford County Building Department page.

A fourth assumes a permit issued in 2025 or 2026 applies the 2021 code. It does not, while the 2015 code remains current; the code edition actually applied is listed on LARA's code-books page.

Frequently Asked Questions

Who issues building permits in Cadillac, Michigan?

The City of Cadillac issues its own building, trade and soil erosion permits through a private contractor it has retained, with applications handled at City offices on N. Lake Street. Outside the city, Wexford County issues permits everywhere except Cedar Creek Township and the City of Manton, which issue their own.

Does a building permit mean the work passed inspection?

No. A permit records that the work was authorized. Inspections and their results are separate entries in the permit file, and final approval appears as a final inspection or a certificate of occupancy.

How long is a building permit good for in Wexford County?

Under section R105.5 of the 2015 Michigan Residential Code, a permit becomes invalid if work does not start within 180 days or is suspended for 180 days. Wexford County's packet adds that a permit is cancelled if no inspections are requested or performed within six months of issue.

Is the 2021 Michigan Residential Code in effect?

Not as of November 2026. It was set to take effect August 29, 2025, but the Michigan Court of Claims stayed it on July 7, 2025 while litigation was pending. The 2015 code remains current; check with LARA for any later change.

Is the 180-day permit rule in 1972 PA 230?

No. The statute sets the 10 or 15 business-day decision deadline. The 180-day validity rule comes from the residential code, section R105.5.

Do I need a permit for a small shed in Wexford County?

As published in the county's Building Information Packet, accessory structures under 200 square feet and under 10 feet high need no building permit, but zoning approval is still required. Inside Cadillac, Manton or Cedar Creek Township, the local office's rules apply.